Extending Utilities Up Flanders Road Would Cost $16.9 Million

Project could be done in phases and would require voter approval at referendum.

Extending utilities up to the Flanders Road industrial area would cost an estimated $16.9 million, the consultant Fuss & O’Neill told the Groton Town Council Tuesday.

The town hired the company in 2005 to give an updated estimate of the cost of running water and sewer along Flanders Road, which has about 108 acres of developable land, according to the report.

The town also wanted to know whether it would be possible to bring the utilities across the Interstate 95 Bridge, and how that might be done.

Virgil Lloyd, a senior vice president with Fuss & O’Neill, said the company would advise hanging the water and sewer lines under the bridge, in between the girders that support the bridge itself. He said they would be sufficiently insulated from cold and movement.

The extension of utilities up Flanders Road is considered an economic development project to encourage industrial and manufacturing development, in light of the recent downsizing by large companies like Pfizer.

The council now must decide whether it wants to attempt a portion of the project or the full project, which could be done in four phases.  The work would require a bond referendum that would need voter approval.

One open question is whether the project would yield enough new businesses and jobs for the town. Town Manager Mark Oefinger said he has not done that analysis recently, but could have it done in the future.

Property owners living along Flanders Road that don't have access to public water and sewer could be assessed a fee to connect to the lines if the utilities are extended in the future.

If done in phases according to the report by Fuss & O'Neill, the project would begin at the south and be extended north, in the following way:

  • From Fort Hill Road to just below Ensign Drive. The area has water but does not have sewer. The cost of extending sewer is estimated at $5 million.
  • From just below Ensign Drive to the northbound I-95 bridge. Extending water would cost an estimated $2.9 million; extending sewer would cost an estimated $2 million.
  • From the northbound 1-95 Bridge through the southbound I-95 bridge crossing. Extending water would cost an estimated $900,000; extending sewer would cost an estimated $1 million.
  • From the I-95 bridge crossing to Noank Ledyard Road. Extending water would cost an estimated $2.2 million; extending sewer would cost an estimated $2.9 million.

The project has been discussed for years, but most recently came to the forefront in Groton about two years ago, when about a half dozen people - mostly business owners - urged the council to make it a priority.

Tim Tylaska, who owns Mystic Business Park, LLC, an industrial park on Flanders Road, said at that time he housed about 30 businesses, some of which would like to expand but cannot due to the lack of public utilities.

Groton's Strategic Economic Development Plan in 2006 ranked the project first on its list of 13 economic priorities.

LegacyMom January 23, 2013 at 10:01 PM
Oh, please. My property values are literally down the drain...pipes across town aren't going to help much in most Groton neighborhoods. Groton Utilities now has the burden of paying off TVC's debt and the Town wants to spend more money to make money?!? Anyone see a pattern here?
Daniella Ruiz January 24, 2013 at 04:10 AM
do they really think property values will skyrocket enough with the transfer/recycle facilty right there? industrial values may rise, but homeowners values will surely drop if traffic increases, noise increases and they install on/off ramps to I-95
Genevieve Cerf January 24, 2013 at 04:18 AM
The committee created to study the Flanders Road utility issue reported that the project would only result in $1 million increase in the Grand List. Given our current mill rate, only $20K additional property tax would be generated. Can anyone divide $17 million by $20K? Yup, it would take 850 years to make our money back! Why do we keep doing these things to ourselves in Groton? :-(
Jay Dempsey January 24, 2013 at 04:27 PM
I agree Genevieve....it is cost prohibitive. We can't afford backwards thinking like "if we build it they will come". Something this expensive would have to be done as a partnership with guarantees from larger corporations moving into the Flanders area. No more mistakes like TVC. Jay Dempsey
William C johnson January 25, 2013 at 09:32 PM
Mrs Cerf, as an RTM member I am amazed that you would make such a ridiculous and untrue statement. Lets do the math 100 acres of industrial land equals a $1,000,000 addition to the grand list . Sorry that doesn't add up. The facts are, the Industrial area this project is being developed for already has buildings valued over $5,000,000, and the area is only about 20% built. In fact the owners have had to do remarkable work just to get to that level. They have had to turn businesses away because they don't have water, and can't expand. These are real jobs, and real homeowners that are not coming to Groton. If you are anti development that's your choice but please bring real facts to support your argument. You owe it to the people you represent to at least give them the truth.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »